| 1. | Sondu Miriu - Kisumu Line
50km 132kV line |
| 2. | Mumias - Rang'ala
34km 132kV line, 2x23MVA 132/33kV sub-station and 6x33kV feeder bays. |
| 3. | Rabai - Galu Line
47km single circuit 132kV line, 2 no. 23MVA, 132/33kV sub-station |
| 4. | Kamburu - Meru Line
122km single circuit 132kV line, 132kV 23MVA sub-station, 4x33kV feeders |
| 5. | Chemosit - Kisii Line
62km single circuit line. 132/33kV sub-station, 132kV 23MVA s/stsn, 5No. 33kV 3 phase feeders |
| Projects Under Implementation | |
|---|---|
| 1. | Thika – Kiganjo (Nyaga)
30km, 132kV Single Circuit Transmission Line and associated substations. |
| 2. | Ishiara - Kieni - Embu
35km 132kV line and 1 No. 23 MVA Sub-station |
| 3. | Sultan Hamud - Wote - Kitui
37km, 132kV Line and 2 No. 5MVA sub-stations |
| 4. | Bomet - Sotik
33km, 132kv line and 1no.23MVA substation |
| 5. | Olkaria - Narok
68km 132kv line and 1no. Substation 23MVA sub-station |
| 6. | Lessos - Kabarnet
65km 132kV line, with 132/33kV, 1x15MVA tx at Kabarnet |
| 7. | Nanyuki - Nyahururu
79km,132kV line with 132/33, 1x23MVA tx at Nyahururu |
| 8. | Eastern Africa Interconnector (Ethiopia - Kenya)
686km 500kV HDVC bipole, 400kV sub-station. Phase 2 upgrade to 2000MW P1-33500, P2-20500 |
| 9. | Olkaria - Lessos - Kisumu
300 km, 220kV double circuit line, 1 No. 90MVA sub-station |
| 10. | Kisii - Awendo
44km 132kV line, No. 1 23 MVA sub-station |
| 11. | Eldoret - Kitale
60km 132kV line, with 1 x 23MVA tx at Kitale |
| 12. | Kindaruma - Mwingi - Garissa
250km 132kV Line and 1 No. 23 MVA sub-station |
| 13. | Nairobi Metropolitan Ring: Sub-stations
Part of the 100km, 400kV, Double Circuit Transmission Line; Suswa – Isinya, & Substations |
| 14. | Nairobi Metropolitan Ring: Suswa – Isinya line
Part of the 100km, 400kV, Double Circuit Transmission Line; Suswa – Isinya |
| 15. | Lessos - Tororo
127km transmission line and 2x75MVA transformers at Lessos. 220 kV double Circuit & upgrading Lessos S/Stn. |
| 16. | Rabai - Malindi - Garsen - Lamu
320km 220kV line and associated sub-stations |
| 17. | Loiyangalani - Suswa
430km 400kV transmission line |
| 18. | Mombasa - Nairobi (Isinya)
475km 220/400kV line and associated sub-stations |
| 19. | Kilimambogo - Thika - Githambo
17km double circuit 132kV line, 50km 132kV line, 132kV double sub-station |
| Projects Planned for Implementation | |
|---|---|
| 1. | Kenya-Tanzania Power Interconnection Project
510-km 400 kV interconnection power line |
| 2. | Kindaruma -Athi River Line
150km 220kV Line and 1 No. 75MVA Sub-station at Kindaruma |
| 3. | Sondu - Kendu - Homa Bay
80Km 132kV single circuit, 2x23 MVA tx at Homa Bay |
| 4. | Baringo - Rongai
80Km 220kV double circuit, 2x75 MVA tx |
| 5. | Arusha - Nairobi
260km ,400kV Line |
| 6. | Konza - Machakos
45km 132kV Line, 1 No. 23MVA sub-station |
| 7. | Konza - Kajiado
45km 132kV Line, 1 No. 23MVA sub-station |
| 8. | Nyahururu - Maralal
--- |
| 9. | Meru - Isiolo - Nanyuki
75km 132kV line, 1 No. 23MVA sub-station |
| 10. | Sub-Station at Mariakani & Isinya
400/220kV Sub-stations works at Mariakani |
| 11. | Suswa & Loiyangalani S/Stns.
Loiyangalani 400kV & Suswa 400/220 kV S/stns. |
| 12. | Nairobi Metropolitan Ring: Suswa - Ngong Line
45km 220kv double circuit Line and 2x90MVA, 220/66kV substation at Ngong |