Olkaria- Narok line. |
68km |
132kV |
N/A |
Ongoing |
View |
Nanyuki- Isiolo- Meru project. |
97km |
132kV |
N/A |
Ongoing |
View |
Nairobi Ring and associated substation. |
103km |
400kV |
N/A |
Ongoing |
View |
Mariakani substation. |
482km |
400/220kV |
N/A |
Ongoing |
View |
Sultan Hamud- Wote |
42km |
132kV |
Jun 2019 |
Completed |
View |
Ndhiwa- Awendo |
37km |
132kV |
Jun 2018 |
Completed |
View |
Kisii – Awendo |
44km |
132kV |
Dec 2017 |
Completed |
View |
Suswa – Isinya (Nairobi Ring) |
103km |
400kV |
Jun 2017 |
Completed |
View |
Mombasa - Nairobi |
482km |
400kV |
Jun 2017 |
Completed |
View |
Ishiara- Kieni |
33km |
132kV |
Dec 2016 |
Completed |
View |
Machakos – Konza |
13km |
132kV |
Nov 2016 |
Completed |
View |
Sotik-Bomet |
26km |
132kV |
Aug 2016 |
Completed |
View |