Financier
KBC Bank of Belgium
Government of Kenya (GoK)
Contractor
CG Holding Belgium N.V
Scope
The project involves the construction of the 97km 132kV single circuit line with 73MW rating from the Nanyuki substation to the Meru substation through the Isiolo substation. The project also involves the construction of a new 132kV substation at Isiolo and the extension of existing substations at Nanyuki and Meru.
Benefit
To extend the transmission and distribution lines as well as new and reinforced distribution lines with the aim of reducing technical losses, stabilizing voltage conditions, and thereby coping with the additional demand.