Status
Ongoing
Length
109 km
Volt
132kV

Financier
EXIM INDIA

Contractor
SHYMA POWER

Scope

153 (Revised to 109) km 132kV Line, 4no. 23MVA sub-stations (Revised to 4Nos. 132/33kV 23MVA sub-stations + 1 No. 220/132kV 90mVA Substation.

 

Benefit

Connect load centers of, Machakos, Konza, Kajiado and Namanga to National Grid so as to improve access to reliable power, and Supply Konza ICT City and the Standard Gauge Railway line.